Update on Multimodal Enhancement Project in Medford

by Jeff Roberts on Feb, 18 2023

Following up on the Petition to support the Multimodel Enhancement in Nov 2022:

There’s a timeline showing on the Public Works page for the study being done by Kittelson, which is now complete.

The Main bike facility implementation timeline looks like:
  • curb ramps along Main could start any day (Contractor is hired and will schedule at their discretion amongst other ramps in the City)
  • paving is scheduled to be complete by August 15
  • striping complete by mid October.
Please keep in mind, while Public Works will do the best they can to keep to this schedule, it is all still subject to change.
The plan for the continued discussion of possible changes on Riverside and Central is to be at the Transportation Commission in April/May and a Council study session in June. Riverside is scheduled for an overlay in 2024 so those discussions will help Public Works better understand the City’s direction forward.
Thanks to Christina Charvat of Medford Public Works dept. for this update.